| Site |
Dock Gate 4 Cruise Terminal, Southampton Docks, Southampton |
| |
|
| Customer |
Dean & Dyball |
| |
|
| Project |
Bulk earthworks and remediation of contaminated ground.
Breaking up of the existing surfaces and the crushing of the resulting 10,000 cubic metres of rubble. Processing then blending for re-use on-site. Areas levelled ready for building contractor. |
| |
|
| Area |
Ten acres |
| |
|
| Timing |
Three months to date (ongoing) |
| |
|
| Results |
Recycled content 99%: No accidents, no near misses |